Customer: Centre National d’Etudes Spatiales (CNES)
Programme: Spot Helios
Supply Chain: CNES > CS Group SPACE
Context
CS Group responsabilities for Support for soil operations of the Helios 2A / 2B post maintenance center are as follows:
- Strengthen CNES teams, maintain CMPs in operational conditions, comply with operational constraints

The features are as follows:
- **Exploitation of CMP **, namely :
- 24 -hour soil penalty: Conf exploitation monitoring. hardware and software
- Monitoring of installations, guarantee of the integrity of software
- Participation in operational meetings
- Supports at the tests of the team, mission, orbito teams
**Technical management of subsystems ** (STS, Dutch, CGCU, EGM, OMGS, FOS/ARPE, CCS, …), namely :
- Software monitoring with regard to the industrial resp. maintenance
- Validation of new versions
- Support for on -call duty if software problems
- Preparation for CNES software monitoring commissions
Project implementation
The project objectives are as follows:
- Ensure operations for the operating floor service for positions to post Helios satellites as a delegation of tasks
- MCO (Maintaining operational conditions) of the Middle Sol used to ensure the operations of satellites in the Helios sector
The processes for carrying out the project are:
Technical characteristics
The solution key points are as follows:
- Maintaining skills to ensure the MCO and support for operations over a very long period
The main technologies used in this project are:
| Domain |
Technology(ies) |
| Hardware environment(s) |
HP-UX, PC |
| Operating System(s) |
Linux RedHat, Windows |
| Interoperability (protocols, format, APIs) |
BPD, FTP, VMWare |
| Production software (IDE, DEVOPS etc.) |
Testlink |
| Main COTS library(ies) |
CRYSPIS, NetBackup |