Customer: Centre National d’Etudes Spatiales (CNES)
Programme: ATV
Supply Chain: CNES > CS Group SPACE
Context
CS Group responsabilities for ATV mission team support are as follows:

The features are as follows:
- Training Instructor: Preparation of tests, creation of scenarios, drafting of plans and follow-up, support to ESA for the preparation of simulations
- Interface with FDS teams
- Planner: Preparation of the flight plan, checking its consistency and transmission to the teams
- Operation Manager: real-time coordination of operations in accordance with the flight plan, management of operational contingencies; interface with partners
Project implementation
The project objectives are as follows:
- Operations support within the ATV team
- Operational pre-Qualification, Operational Qualification and ATV operations phases
- Support to the Mission team for the roles of Training Instructor, Planner, Operation Manager
The processes for carrying out the project are:
Technical characteristics
The solution key points are as follows:
- Means of the ATV control center
- Mastery of the components of the ATV mission
- Operational planning
- Continuity of service 24 hours a day during the flight phases, team of 11 engineers (average)
The main technologies used in this project are:
| Domain |
Technology(ies) |
| Hardware environment(s) |
PC |
| Operating System(s) |
Linux |
| Programming language(s) |
KornShell, SCILAB |
| Production software (IDE, DEVOPS etc.) |
cygwin, oscar, doors |